Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 52 In this issue we get a circuit board and a spacer for the foot sensor of the first leg. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Elite Groups: Registered
Joined: 20/04/2012 Posts: 1,787 Points: 5,292 Location: Thurso
|
Hi, looking through your post for Issue 49, I think you have fitted the inner wheel support plate to the wrong side of the leg frame. It is worth checking as the covers won't fit if you have.
Graeme
|
|
|
Coming together nicely, looking good.... Regards Alan
|
|
|
Looking good Mark
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
pemberg wrote:Hi, looking through your post for Issue 49, I think you have fitted the inner wheel support plate to the wrong side of the leg frame. It is worth checking as the covers won't fit if you have.
Graeme Thanks for that, I have now changed it and updated the pictures for Issue 49 Peter Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Here we go with the next 4 issues. Issue 53 In this issue we get a test board and 2 cables to test the lightsaber, the leg sensor & the foot sensor. All of mine work with no problems Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 54 We have the final foot bracket and bearing, and 3 panels for the dome. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 55 More screws and the motor for the leg. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 56 This issue we have 1 half of the leg cover, 2 more panels for the dome & the powerbus cable mounting plate. Ritchie69 attached the following image(s): Completed - R2D2
|
|
|
Doing a great job and very well presented too.... looks fab.... Regards Alan
|
|
|
Great update, nice to plenty of pictures. Coming on very nicely. Mark
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Thanks. It’s a really enjoyable build. I’m looking at building the Rossi bike once it comes out (fingers crossed). Now that I know the quality of the parts. Peter Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
These 4 issues we finish off the second leg & make good progress on the dome. Issue 57 We have another dome panel to fit. Also the sensor for the foot and the foot casing. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 58 Another dome panel. The foot base plate & powerbus cable. The powerbus cable will be stored away to be used in another issue. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 59 And another dome panel to fit (there's quite a lot of them) and the fuel cell covers. Also fit the powerbus cables from the previous issue. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 60 We have the shoulder fitting & a top panel for the dome to be stored away for a later issue. The electric cable is to be fitted onto the logic function display, then stored until fitted inti the dome. more plastic plugs for the leg. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Its that time again, the next 4 issues have arrived. There is more things to do in these issues, with attaching a few of the previous issue parts. Issue 61 In this pack we get another leg fitting and more panels for the dome. Plugs for the leg and some more screws. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 62 We get dome panels, the camera & projector mountings. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 63 We get more dome panels, the top panel for the dome and some spacers. Ritchie69 attached the following image(s): Completed - R2D2
|
|
Rank: Pro Groups: Registered
Joined: 29/01/2017 Posts: 177 Points: 546 Location: Corby, UK
|
Issue 64a We get the last of the dome panels and the hinge, and more screws and some plastic allen bolts. Ritchie69 attached the following image(s): Completed - R2D2
|
|